Week 1 Checking the site

5 01 2015

The house demolition finished late November/early December 2014, with some oversized footings discovered and requiring the extra cost of a rock breaker brought on site.

We selected our builder around the same time and they got started before Christmas planning the site works for a 2015 January start.

After demolition, the builder took some levels of the block and not surprisingly found the site levels slightly lower than the levels shown on the survey plan (the survey done pre-demolition when there was still a house on the block, which the architect used for indicating levels on their plans).

So, it was proposed to lower the height of the slab as shown on the architects plan by around 100mm to minimise the cut and fill process and avoid bringing in extra soil rather than working to the architect’s plans which would require soil to be brought in the maintain the proposed slab height. We’re happy to use the natural fall of the block and minimise the soil disruption.

The builders also mapped out the builder edges with blue spray paint on the ground. It’s fun to see where the house is going to be!

Block cleared, builders marked out the house with blue paint on ground.

Block cleared, builders marked out the house with blue paint on ground.

Advertisements

Actions

Information

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s